4.00 minutes – 940KB
VI. FINANCIAL CONSIDERATIONS
A. CONSIDER APPROVAL OF RES. #646-09-142
RE: AUTH. PAYMENT – VARIOUS DEPTS.
B. CONSIDER APPROVAL OF RES. #647-09-142
RE: TRANSFER OF FUNDS – VARIOUS DEPTS.
C. NOTE RECEIPT OF AN AMENDED CERTIFICATE RE: TAX BUDGETS – 2010
General Fund Certificate for 2010 is $9,973,928.00
D. CONSIDER APPROVAL OF RES. #648-09-142
RE: TEMPORARY APPROPRIATION – 2010
Chris – Question on if they have received an amended certificate for this year (2009). Expected to be in the neighborhood of $9,17?,???.
End 15 minute mark
11 minutes – 2.51MB
Variety of subjects.
Issue of $63,000 grant that would help fund OSU Extension at 20 minute mark.
Tower rental at Fairground at 23 minute mark.
End 28.75 minute mark
13.44 minutes – 3.14MB
9:30 A.M. – PUBLIC HEARING – ZONING CASE #1271 – JAMES WILLIAMS, ESTATE
There will be a transcript of this meeting.
End 37.75 minute mark
9 minutes – 2.06MB
End 43.75 minute mark
6 minutes – 1.37MB
Dave to recuse himself on the RFQ's discussion
Chris – $9,418,756 amended budget.
End 49.25 minute mark
5 minutes – 1.26MB
LEACHATE ISSUE
Bob – scoring system fair and proposals speak for themselves. Pay attention to recommendation of committee we formed.
Dave – Not in total agreement, believes there is a benefit in the future for Camden and county. Urban transition area and with rail available is better positioned to growth.
Camden application lacks detail and could have been done better.
Bob – continues to feel the recommendation of the committee.
Dave – (59 minute mark) felt that originally the discussion was with Camden. The meeting did not go well, there was a feeling of arrogance as to the price Camden should get and other options were opened.
Chris – Options included building treatment facility on site at landfill. We can only base our decision on what was submitted.
Dave – Pricing was put at 50 points and feels should have been scored higher than 15 points and that was split into three areas. 1 hr. 4 min. mark.
Bob – Price over 80 years to landfill should be considered
Dave – question on pretreatment.
Chris – On this process we did not get into the engineering of it.
Dave – Lakengren did a very professional presentation and he is disappointed with Camden's.
Chris – on two options follow process or throw them out and start over.
Bob makes recommendation to open negotiations with Lakengren.
Dave seconds motion.
Motion passed 3 – 0
Deadline for Committee of two weeks
End 1 hr. 21.8 minute mark
31.38 minutes – 7.24MB
Fairgrounds discussion relative to Pork Festival and Fair
Chris – Opens with question on status of Fair Board and study.
Dave – wanted to back out of being involved. Had not heard boo out of Woolpert since the evening meeting.
Bob – we can't be doing something on our own while have Woolpert doing a study. Wait on study, same as Leachate. Plan does not need to be accepted.
Dave – reminds Bob of his stance on Leachate issue.
1 hr. 29 min. Courthouse Christmas tree
1 hr. 33 minute mark Dave recuses himself because of close friendship with one of the people working for a company submitting RFQ's on Goose Creek and leaves chambers.
1 hr. 37 minute mark – Bob on Poggemeyer (not happy with the way they have handled grant issue). Would like to make decision that afternoon.
1 hr. 41 min. mark Chris back to Fairboard issue.
Bob – probably should not have said we don't have to accept their recommendation.
Chris – We are entrusted to do what is best for the residents of Preble County.
End 1 hr. 44 minute mark
23.03 minutes – 5.27MB
*** Audio from 1hr. 44 minute mark to 1 hr. 58.50 minute mark – office noise and chatter)
11:00 A.M. – SHERIFF SIMPSON (SHERIFF’S ROTARY FUND)
End 2 hr. 10 minute mark
23.03 minutes – 5.27MB
End 2 hr. 27.8 minute mark
17.53 minutes – 4.09MB
11:30 A.M. – PAT TAYLOR (GOVERNOR ANDREW HARRIS)
End 3 hr. 14 minute mark
46.12 minutes – 10.5MB
Recess
Back in session
Commissioner Wesler has recused himself.
Goose Creek Crossing
Narrowed to three companies. They will be brought in for interviews on December 14. They are:
1:00 P.M. – ME COMPANIES – RFQ GOOSE CREEK CROSSING PROJECT
2:00 P.M. – KLEINGERS & ASSOCIATES – RFQ GOOSE CREEK CROSSING PROJECT
3:00 P.M. – WOOLPERT, INC. – RFQ GOOSE CREEK CROSSING PROJECT
Grant of $15,000 available to Sheriff's Department, no match required.
*** Chris on insurance document from Fair Board. Fair Board Manager Duane Grimme responsible. Fair Board President Mr. Kimball. Commissioner need it signed.
End 3 hr. 30 minute mark
16 minutes – 3.66MB
*** Audio removed from 3 hr. 30 min mark to 4 hr. 12 minute mark, (background office noise, lack of voice audio) ***
Chris – brought Katie up to speed on the Leachate.
Chris – Matt called me and wanted to have lunch.
Bob – concern over trip to Van Wert (This was previously mentioned as another way to see how economic development is done. Van Wert uses OSU Extension and funds it with a lodging tax. That income was down significantly in 2009 and a levy was put on the ballot.)
End 4 hr. 2.23 minute mark
9.45 minutes – 10.5MB